SARASOTA
MEMORIAL HOSPITAL
Emergency Care Center
Sarasota, Florida
The Emergency Department expansion
project was significantly over budget, and the schedule was in
jeopardy. Upon our hiring, we instituted an aggressive cost
reduction program and negotiated a significantly lower GMP
with the contractor to bring the project back within budget.
The expansion was constructed immediately below the
hospital's 16 OR surgical suites and adjacent to its
existing Emergency Department. The use of microscopes in
several of the Surgical Suites required the project team to
coordinate and communicate very closely with the surgical
and ED staff. There were no incidents of compromised safety
or infection control during the construction process, and
the project was completed on schedule and in budget.
|
|
 |
|
|
Project Description:
Emergency Department Expansion
Construction Cost: $8 million
Total Project Cost: $12 million
Status:
Construction Completed Feb 2005
Principal/Project Manager:
Joe Collins
Architect:
The Ritchie Organization
General Contractor:
Keyco, Incorporated
 |
|
|