This project is the completion of two Athens Clarke County
Unified Government’s 2005 SPLOST project which was funded
over a three year period. By establishing a great project
Team, utilizing the Design Build approach, and working with
a cooperative government and citizens of the Athens Clarke
County Unified Government, this project was constructed in
less than a year, met all program requirements and was
completed under budget.
The project consisted of adding a partial second level of
approximately 10,000 square feet to the Classic Center’s
existing Exhibit Hall. On this new level, which connected
directly to the main Classic Center meeting rooms, was
located two large meeting spaces each capable of being
dividing in half, a pre-function corridor, food service
spaces, restrooms and ancillary offices. All spaces were
equipped with state-of-the-art lighting controls and
audio-video capabilities. Below this new level, utilizing a
system of moveable partitions, five breakout spaces were
created each with similar lighting controls and A/V
capabilities as the upper spaces.
A significant component of this project was the erection of
a pedestrian bridge from the new Upper Level, across Foundry
Street and tying into the Foundry Street Warehouse which
houses additional meeting/breakout spaces. This bridge
connection included an extension of the Warehouse elevator
up to the bridge level making, for the first time, an
accessible connection between the two Classic Center
facilities.
|
|
 |
|
|
Project Description
Renovation to Classic Center
Construction Cost: $5 million
Total Project Cost: $6.2 million
Status
Construction Complete November 2006
Principal-in-Charge:
Marcus Vess
Project Manager:
Kenneth Crellen
Architect
Rosser International
Contractor
Choate Construction
 |
|
|